Mon 14 September, 2026

Contract Law Case: Department of Road vs. Himal Construction Company. NKP, (4th Semester).

Contract Law Case: Department of Road vs. Himal Construction Company. NKP, (2066), No. 8, P.288, D.N: 8054

 

Case: Certiorari, privity of contract.
Plaintiff: The Department of Roads (Ministry of Physical Planning and Works).
Defendants: Patan Appellate Court, Rara Construction (P) Ltd., Himal Construction & Builders (P) Ltd., and The Gorkha Engineers & Services International (P) Ltd.
Decision Number: 8054

 

This case is related to issue of Writ of Certiorari, privity of contract, Arbitration, Locus Standi.

 

Facts of the Case:
The Department of Roads (DoR) entered into two separate, independent contracts with Rara Construction and Himal Construction for road and bridge construction projects. These main contractors (Rara and Himal) hired a third company, The Gorkha Engineers, as a sub-contractor to perform the actual construction work. The Department of Roads later terminated the main contracts with Rara and Himal after discovering that they had submitted fraudulent documents. Following the termination of the main contracts, The Gorkha Engineers (the sub-contractor) claimed they suffered significant financial losses. They filed a claim for compensation and demanded the appointment of an arbitration tribunal to resolve the dispute with the Department of Roads

Plaintiff’s Claim:
The Department argued that there was no contractual relationship with “The Gorkha Engineers.” The sub-contractor has no right to demand arbitration against the Department, as their legal obligations are strictly with the main contractors (Rara and Himal).

 Defendant’s Argument:
They argued that since the main contractors granted them full authority to execute the work and receive payments, they essentially stepped into the shoes of the main contractors and are entitled to claim damages through arbitration.

 

 Legal Issues:

  1. Does a sub-contractor have the legal standing (locus standi) to demand arbitration against the primary employer (the Department of Roads) when the sub-contractor is not a party to the original contract?
  2. Is a third party (sub-contractor) entitled to trigger dispute resolution mechanisms provided in a contract to which they are not a signatory?

 

 Decisions of the courts:
Arbitration Tribunal:
Initially ruled that the sub-contractor had no legal right to sue the Department of Roads.

Patan Appellate Court:
Overturned the tribunal’s decision and ordered a new arbitration process to begin.

Supreme Court:
Supreme Court upheld the original decision of the arbitration tribunal and quashed the order of the Appellate Court. It ruled that since there was no direct contract between the Department of Roads and The Gorkha Engineers, the sub-contractor had no legal basis to demand arbitration against the Department.

 

 Established Principles:

  1. Doctrine of Privity of Contract: A contract cannot confer rights or impose obligations upon any person who is not a party to it.
  2. Limited Liability of Sub-contractors: A sub-contractor’s legal relationship is strictly limited to the party with whom they signed the sub-contract. If they suffer losses due to the cancellation of the main contract, they must claim damages from the main contractor, not the primary project owner.
  3. Right to Arbitration: The right to appoint an arbitrator or demand arbitration is reserved only for the parties to the original contract.

 

 

How did this news make you feel?
0
0
0
0
0
0

About Author

Picture of Entertain Lawyers

Entertain Lawyers

Entertain Lawyers is Nepal’s trusted legal news platform, dedicated to delivering unbiased legal updates, court news, and informative content for legal professionals and the general public.
Picture of Entertain Lawyers

Entertain Lawyers

Entertain Lawyers is Nepal’s trusted legal news platform, dedicated to delivering unbiased legal updates, court news, and informative content for legal professionals and the general public.

Related Post

error: Content is protected !!