Thu 03 September, 2026

Contract Law Case: Nepal Electricity Authority vs. Modern Malewalls Ltd., NKP (5th Semester Old Syllabus)

Contract Law Case: Nepal Electricity Authority v. Modern Malewalls Ltd. SC, 2063, Part 4, P. 518.

 

Case: Contract of Guarantee, Bank Guarantee, Arbitration, Jurisdiction of Arbitral Tribunal, and Certiorari
Petitioner: Nepal Electricity Authority, Baluwatar, Kathmandu
Respondent: Modern Malewalls Ltd., Nepal Bank Limited, Arbitration Tribunal, Patan Appellate Court.
Case Number: 073-NF-0047

 

This case is related to Contract of Guarantee, Bank Guarantee, Arbitration, Jurisdiction of Arbitral Tribunal, and Certiorari

 

Facts of the Case:
Nepal Electricity Authority and Modern Malewalls Ltd. entered into a contract on 2050/07/24 BS  under which Modern Malewalls was required to supply 18,383 km of ACR conductor wire to NEA within 18 months. The agreed contract price was US$6,676,734. The contract provided for supply in stages, but Modern Malewalls supplied only about 18.21% of the required wire. After supplying that portion, Modern Malewalls demanded an 80% increase in the agreed price and stated that it would not supply the remaining wire unless NEA accepted the increased price. NEA rejected the demand because the contract terms did not permit such a change in the agreed price. NEA subsequently gave notice requiring Modern Malewalls to continue supplying the wire, but the company did not do so. NEA therefore terminated the contract and, after termination, requested Nepal Bank Limited to pay the amount covered by the bank guarantee.  Modern Malewalls then initiated arbitration proceedings concerning the dispute arising from the termination of the contract. During the arbitration proceedings, the Arbitration Tribunal issued an order directing Nepal Bank not to pay the bank-guarantee amount to NEA. NEA challenged this order before the Patan Appellate Court, but the Appellate Court upheld the Tribunal’s decision. NEA therefore approached the Supreme Court through a certiorari writ petition, challenging both decisions.

 

Petitioner’s Claim:
NEA argued that the Arbitration Tribunal had acted beyond its jurisdiction. The arbitration was established to resolve the dispute between NEA and Modern Malewalls regarding the supply contract.  The bank guarantee was a separate and independent contract between NEA and Nepal Bank. Therefore, the Arbitration Tribunal could not issue an order preventing Nepal Bank from paying the guarantee. The Tribunal had also made the decision without properly hearing NEA and that decision interfered with NEA’s contractual rights under the bank guarantee. The Patan Appellate Court was therefore wrong in upholding the Tribunal’s decision.

 

Respondent’s Arguments:
The respondents argued that the Arbitration Tribunal had authority under the Arbitration Act, 2038 to issue an interim order. The dispute was connected with the contract between NEA and Modern Malewalls, so the Tribunal’s order concerning the guarantee was related to the dispute. Contractual rights did not provide a sufficient basis for invoking the Supreme Court’s extraordinary writ jurisdiction. Therefore NEA’s writ petition should be dismissed.

 

Legal Issue:

  1. Whether NEA had locus standi to challenge the Tribunal’s order through a writ petition?
  2. Whether the bank guarantee was an independent contract or merely part of the main contract between NEA and Modern Malewalls?
  3. Whether the Arbitration Tribunal had authority to order Nepal Bank not to pay the bank guarantee?
  4. Whether the decision of the Arbitration Tribunal and the order of the Patan Appellate Court should be quashed?

 

 

Decision of the Courts:
Arbitration Tribunal: The Arbitration Tribunal ordered Nepal Bank Limited not to pay the bank-guarantee amount to NEA.

Patan Appellate Court: The Patan Appellate Court upheld the decision of the Arbitration Tribunal.

Supreme Court: The Supreme Court quashed the decision of the Arbitration Tribunal and the order of the Patan Appellate Court and stated that the bank guarantee was an independent contractual relationship between NEA and Nepal Bank. The guarantee was not simply another term of the underlying supply contract between NEA and Modern Malewalls. The Court also held that an arbitral tribunal is constituted to decide the disputes within the scope of the matters referred to it. It cannot extend its authority to determine or interfere with an independent contractual relationship involving a third party without proper authority. Therefore, the Tribunal could not prevent Nepal Bank from performing its obligation under the independent bank guarantee merely because there was a dispute between NEA and Modern Malewalls concerning the underlying supply contract.

 

Established Principles:

  1. Bank guarantee is an independent contract: A bank guarantee creates an independent contractual relationship between the bank and the beneficiary. It is separate from the underlying contract between the beneficiary and the contractor.
  2. Dispute in the underlying contract does not automatically suspend the bank guarantee: A dispute between NEA and Modern Malewalls regarding the supply contract does not, by itself, permit the contractor or an arbitral tribunal to stop the bank from performing its obligation under an independent guarantee.
  3. Decision beyond jurisdiction is invalid: Where a tribunal acts beyond its legal authority, its decision can be challenged and quashed through appropriate judicial review.
  4. Main contract and bank guarantee are separate contracts; an arbitrator dealing with the main contract cannot automatically interfere with the independent bank guarantee.”
How did this news make you feel?
0
0
0
0
0
0

About Author

Picture of Entertain Lawyers

Entertain Lawyers

Entertain Lawyers is Nepal’s trusted legal news platform, dedicated to delivering unbiased legal updates, court news, and informative content for legal professionals and the general public.
Picture of Entertain Lawyers

Entertain Lawyers

Entertain Lawyers is Nepal’s trusted legal news platform, dedicated to delivering unbiased legal updates, court news, and informative content for legal professionals and the general public.

Related Post

error: Content is protected !!